Six Cineplex Project
Primary Proposal Presentation β’ Galaxy Media Company
www.gmostafa.com
www.galaxymediaus.com
End-to-End Execution
Client: Galaxy Media Company
Contractor & Consultant: G. Mostafa Trade .
Scope: Site visit, soil testing, 2D/3D drawings, civil works, MEP, HVAC, fire fighting, lighting, interior, plumbing, playground + foot court.
Promise: Turnkey cineplexes with modern cinema experience.View Primary Quote β

Primary Land Assessment

Locations: Rajshahi, Naogaon, Sylhet, Comilla, Khulna, Bogra
Areas mentioned are provisional β final measurement after site visit. We adjust design accordingly.
| Cineplex Name | Primary Land (Katha) | Status |
|---|---|---|
| ποΈ Rajshahi Cineplex | 5 katha | To be verified |
| ποΈ Naogaon Cineplex | 4 katha | To be verified |
| ποΈ Sylhet Cineplex | 3 katha | To be verified |
| ποΈ Comilla Cineplex | 5 katha | To be verified |
| ποΈ Khulna Cineplex | 5 katha | To be verified |
| ποΈ Bogra Cineplex | 5 katha | To be verified |
Note: Primary areas may change, final quotation after actual site measurement.
Design Concept | How It Looks
Modern glass facade, digital signage, integrated playground & foot court. Each cineplex has a unique identity.

Day Facade β Digital Display & Glass

Night View β Neon lighting & landscape

Lobby + Ticketing & Concession

Playground + Foot Court (walkway & kiosks)
Unique naming per location: e.g., “Rajshahi Cine Square”, “Naogaon Galaxy Cine”, “Sylhet Cine Garden”, “Comilla Silver Screen”, “Khulna Cine Harbor”, “Bogra Cine Oasis”.
Each includes 1 main auditorium (150-200 seats) + mini hall (80 seats), plus playground and foot court essential zone.
Workflow β Drawing to Construction
2D & 3D Drawings
Detailed floor plan, elevation, parking, playground zoning. 3D realistic rendering for client approval.
Construction Phases
Site preparation β Foundation β Superstructure β Finishing. Quality checks at every stage.
MEP + HVAC Integration
Mechanical, Electrical, Plumbing, VRV/VRF AC, fire fighting, acoustic ceilings.
Interior & Lighting
Acoustic panels, theatre lighting, lobby design, emergency lighting + client walkthrough.
Consultancy & Systems (MEP | HVAC | Fire Fighting)
HVAC: Energy-efficient VRV/VRF systems, zoned for auditorium & lobby.
Fire Fighting: Wet riser, sprinklers, smoke detectors, fire alarm + emergency exit plan.
Lighting: DALI dimming, facade LED strips, emergency backup.
Plumbing: STP, water harvesting, efficient drainage.
Acoustics: Soundproof walls, floating floor for zero echo.

Integrated MEP design for safety & comfort
Primary Quotation (BDT)
*Approximate costs based on primary land area, final after site measurement.
| Cost Component | Rajshahi (5K) | Naogaon (4K) | Sylhet (3K) | Comilla (5K) | Khulna (5K) | Bogra (5K) |
|---|---|---|---|---|---|---|
| Location Visit Fee | 50,000 | 50,000 | 50,000 | 50,000 | 50,000 | 50,000 |
| Soil Test & Survey | 40,000 | 40,000 | 40,000 | 40,000 | 40,000 | 40,000 |
| 2D & 3D Drawing Fee | 350,000 | 350,000 | 350,000 | 350,000 | 350,000 | 350,000 |
| Construction (Civil) | 190 Lakhs | 180 Lakhs | 175 Lakhs | 190 Lakhs | 190 Lakhs | 190 Lakhs |
| MEP + HVAC | 60 Lakhs | 55 Lakhs | 50 Lakhs | 60 Lakhs | 60 Lakhs | 60 Lakhs |
| Fire Fighting | 8 Lakhs | 7 Lakhs | 6 Lakhs | 8 Lakhs | 8 Lakhs | 8 Lakhs |
| Interior + Lighting | 60 Lakhs | 55 Lakhs | 50 Lakhs | 60 Lakhs | 60 Lakhs | 60 Lakhs |
| Playground + Foot Court | 25 Lakhs | 22 Lakhs | 20 Lakhs | 25 Lakhs | 25 Lakhs | 25 Lakhs |
Total Primary Estimate (All six sites): ~ BDT 20 Crore β 21 Crore
*Excluding VAT and taxes, Furniture, Land, Digital Equipment etc.. subject to final design and market rate.
Core Equipment & Materials List
Cinema Experience
- 4K Digital Cinema Projector (Barco/Christie)
- 40ft x 20ft Silver Screen
- Dolby Atmos / 7.1 Sound (JBL/QSC)
- Recliner + High-back pushback seats
Infrastructure
- 100 KVA Generator backup
- VRV/VRF HVAC units
- Fire alarm & suppression system
- POS ticketing + snack bar integration
External Features
- Synthetic grass playground
- Foot court paving + food kiosk area
- LED facade lighting & digital signage

Agency Suggestions β Upgrade & Value Addition
Solar Panel Integration
Roof-top solar reduces 30% electricity cost, qualifies for green rating & long-term savings.
Mixed-Use Foot Court
Rent out shops to local brands β creates passive income for Galaxy Media.
Pilot Project Approach
Start with Sylhet (3 katha) as prototype β faster execution, then replicate to 5k sites.
VR Walkthrough
Before construction, we provide virtual 3D tour for final approval β minimize change orders.
G. Mostafa Trade Advisory β We recommend phased investment, premium acoustics, and fire safety beyond standard. Our consultancy ensures future-proof cinemas.
Proposed Timeline (Post-Agreement)
- Week 1-2: Site visits + soil reports
- Week 3-4: 2D/3D concept drawings
- Month 2-6: Civil construction
- Month 7-9: MEP, HVAC, Fire, Interior
- Month 10: Playground + finishing & Handover
Letβs discuss next steps β
Contact G. Mostafa Trade | www.gmostafa.com | For Galaxy Media, we guarantee quality & transparency.
Β© 2025 G. Mostafa Trade Company β Contractor & Consultant for Galaxy Media Cineplex Project
Primary Proposal | Amounts are estimates subject to verification | Designed for presentation purpose
gmostafa.com Β Β |Β Β galaxymediaus.com